K-IV water supply project to be completed in Oct 2023

Author: Monitoring Desk

The construction work of the Greater Karachi Water Supply Project would start in 3-4 months and would be completed in October 2023. This was informed in a meeting held to review the progress of Greater Karachi Water Supply Project K-IV on Friday. Minister for Planning and Development and Special Initiatives Asad Umer chaired the meeting while Additional Secretary Development Abdul Aziz Uqaili, Project Director Amir Mugal, and Project Consultants Dr Bashir Lakhani and senior officials attended the meeting.

The project director briefed the minister about the revised PC-1 of the K-IV project, the project components, and design details. It was informed in the meeting that WAPDA has completed the revised design of 650 MGD K-IV to be executed as phases.

The project is to commence in 3-4 months, to be completed by October 2023. All planning, design, and procurement activities are as per the project timeline, and the construction of this project will be completed by October 2023. He also advised ensuring an uninterrupted power supply to operate the pumping stations and to supply water to the proposed reservoirs.

The project director informed the chair that the design of the K-IV project has been developed with a modular approach in which five pumping stations with five large mild steel pipes of 84 inches pipes each carrying 130 MGD with a total capacity of 650 MGD have been planned to be executed. The chair was informed that WAPDA has submitted PC-1 with a modified design of 650 MGD K-IV Project with various options for execution of the project, which can be done in phases.

The minister directed the planning division to expedite the processing of this revised PC-1 to get it approved as early as possible by the Central Development Working Party (CDWP) and the Executive Committee of the National Economic Council (ECNEC). The minister expressed satisfaction over the pace of progress and work on the development of revised planning and design of this project which is in line with the prime minister’s commitment to ensure water availability to the residents of Karachi in the shortest possible time.

Share
Leave a Comment

Recent Posts

  • Business

Stocks reach new record high with 500-point rally

The 100-Index of the Pakistan Stock Exchange (PSX) continued with bullish trend on Friday, gaining…

5 hours ago
  • Business

KP govt asked to abolish 2% cess on exports

Members of the Sarhad Chamber of Commerce and Industry (SCCI) Executive Committee on Friday demanded…

5 hours ago
  • Business

Gold prices up by Rs1,300 to Rs267,700 per tola

The price of 24 karat per tola gold increased by Rs.1,300 and was sold at…

5 hours ago
  • Business

Weekly inflation up by 0.55pc

The weekly inflation, measured by the Sensitive Price Indicator (SPI), went up by 0.55 percent…

5 hours ago
  • Business

Rupee gains 8 paisa against dollar

The Pakistani rupee on Friday appreciated by 08 paisa against the US dollar in the…

5 hours ago
  • Business

Commerce minister pledges support for textiles sector

Federal Minister for Commerce Jam Kamal Khan on Friday pledged support for textiles and apparel…

5 hours ago