SC orders forensic audit of Thar coal power project

Author: Daily Times Monitor

The Supreme Court on Thursday directed the National Accountability Bureau (NAB) to probe Thar underground coal gasification project, a private TV channel reported.

A three-judge bench headed by Chief Justice Mian Saqib Nisar heard the suo motu case regarding Thar coal power project. Prominent scientist and chairman of underground coal gasification project in Thar Dr Samar Mubarakmand appeared for the hearing.

The bench ordered the auditor general to conduct forensic audit of the project and submit a report within 15 days. The Sindh chief secretary was directed to seize the project’s belongings.

“The project’s feasibility report is not clear. It was said that 10,000MW of electricity will be produced for 30 years, but according to experts the project will lower underground water reserves and affect the environment,” court adviser Salman Akram Raja informed the bench. “One committee has said that this is a failed project and more funds should not be allocated for it. Those who approved the project should have also looked into it,” he added.

At this, the chief justice said, “For the first time I have realised what a billion is. Billions of rupees were spent like [dried] leaves fly from a tree. Rs 3.8 billion have already been spent on this project and who is responsible for this? Does Dr Mubarakmand have to pay this money?” he asked.

Where did Dr Mubarakmand’s tall claims go? Should this matter not be sent to the Federal Investigation Agency (FIA) or a fresh investigation be initiated? “Justice Nisar questioned the court adviser. “A lot of noise was created over the project that something not done by any scientist before was done this time,” the chief justice said. “A 100MW project is not generating even 3MW of electricity,” he lamented.

“Pakistan is a poor country and is this how we will continue to waste our money? There are two ways of producing electricity from Thar underground coal gasification project – either through coal or by operating the way plants set-up on the ports do,” the chief justice said.

NAB prosecutor Asghar Haider then submitted a report regarding the projects before the bench. “According to engineers, it is not possible to generate electricity from underground coal gasification,” it said.

Court advisers Salman Akram Raja and Shehzad Elahi also submitted their recommendations, following which the chief justice asked about the positions of the federal and Sindh governments on the matter. The advocate general Sindh informed the court, “The project was entirely funded by the federal government and only the land belongs to the Sindh government.” Dr Muabarakmand then said, “The project did not cause any environmental degradation. An Australian company was also working on an underground gasification project … lawyers cannot judge this project.”

“I knew you will say this,” Justice Nisar said in response to Dr Muabarakmand. “When you made these claims, they were romanticised and it was said that free electricity will be provided but the national exchequer suffered a loss of Rs 4 billion.”

Published in Daily Times, October 19th 2018.

Share
Leave a Comment

Recent Posts

  • Pakistan

Metrix Pakistan Empowers Youth with Second Edition of Youth Summit in Haripur

Metrix Pakistan, a pioneering force in technology and innovation, reaffirmed its commitment to youth empowerment…

29 mins ago
  • Business

APBF asks govt to announce special incentives for cash-strapped SMEs to save economy

The All Pakistan Business Forum (APBF) has asked the government to announce special incentives for…

2 hours ago
  • Business

Turkmenistan to complete TAPI energy project with regional countries

Turkmenistan is committed to complete the Turkmenistan–Afghanistan–Pakistan–India (TAPI) energy project together with the regional countries.…

2 hours ago
  • Business

Wheat prices plummet in Punjab as govt delays procurement

Wheat prices in Punjab have plunged below PKR 3,000 per maund (approximately 37 kilograms) due…

2 hours ago
  • Business

Govt forms committee for revival of Pakistan Steel Mills

The Federal Ministry of Industry and Production on Saturday constituted an 8-member committee to revive…

2 hours ago
  • Business

Minister condemns unilateral urea fertilizer price hike

Federal Minister for Industries and Production Rana Tanveer Hussain on Saturday has condemned the unilateral…

2 hours ago